Pool Shed Wiring in Vaughan: Making Room for a New Door

Electrical panel and pool pump timer in a Vaughan pool shed

The owner was adding a new door in this Vaughan pool shed, so the electrical lines in the way had to move first: the wiring for the pool pump and its timer, the ground wire and all the sprinkler lines. Here’s the job in under a minute.

The job

The shed has its own electrical panel, a pool pump with its timer, and the controller for the sprinkler system. With a door going in, every electrical line in its path had to come out of the way. Our part was moving that wiring and reconnecting all of it.

What we did, step by step

  1. Re-fed the pool pump and its timer. Both had to be fed back to the panel. We put in a new junction box, moved the existing wires into it and ran new wiring from there.
  2. Extended the ground. The pool equipment ground had to be extended to make room for the door. We added new bare copper wire with a new grounding connector, then ran the ground back and reconnected it to the panel.
  3. Labelled every sprinkler wire. Before the sprinkler lines came off, we marked every single one individually.
  4. Moved the sprinkler lines. We moved the sprinkler system’s box clear of the door opening and re-routed all the low-voltage sprinkler lines.
  5. Reconnected and ready to go. With every wire labelled, each line went back to the right place on the controller, and everything was ready to go.

Why the labels and the ground matter

The labels. A sprinkler controller has a thin low-voltage wire for each zone, and they all look alike. Swap two and the wrong zone waters, or a zone doesn’t come on at all. Labelling every wire before it comes off is what lets each one go back where it belongs.

The ground. The ground wire is a safety connection for the pool equipment. When the wiring moves, the ground has to move with it and stay connected back to the panel. Here it was extended and reconnected at the panel.

In Ontario, this is work for a licensed electrical contractor, with an ESA permit where required.

When to call an electrician

  • You’re adding a door, a window or a wall where wiring already runs.
  • Pool equipment, like a pump or its timer, has to move or be re-fed.
  • A sprinkler controller has to move, and every zone wire has to go back in the right place.
  • You’re not sure which wire feeds what in your pool shed.

Thinking about a hot tub as well? Our guide to hot tub electrical requirements covers GFCI protection, bonding, permits and panel capacity. You can also read about our residential electrical services.

FAQ

Can you move wiring to make room for a new door?

Yes. In this Vaughan pool shed, we re-fed the pool pump and its timer, extended the ground and ran it back to the panel, and moved every sprinkler line so the owner could add a door. Every wall is different, so we look at what runs through it before planning the new route.

Why label every sprinkler wire?

Because they look alike, and mixing two up sends water to the wrong zone. On this job we marked every single one before moving them, so none got mixed up when they went back on the controller.

Do you do pool and backyard wiring in Vaughan?

Yes. This job was in Vaughan, and we work across Toronto and the GTA. See our page for electricians in Vaughan.

Need pool or backyard wiring moved?

Murtex Electric Inc. is a licensed electrical contractor (ESA/ECRA licence 7016854) led by a licensed Master Electrician who has 13+ years of total experience in the electrical trade. We take care of ESA permits where required, across Toronto and the GTA.

Call or text (647) 529-2972, or request a quote online.

Other Articles

Get Your Quote Today!

Fill out the form below and one of our team members will get back to you within 24 hours.

Modern home entrance with exterior pot lights and landscape lighting
Murtex Electric Inc. is a BBB Accredited Business with an A+ rating - view our BBB business profile
BBB Accredited Business · A+ Rating
Licensed Electrical Contractor · ECRA/ESA #7016854 · ESA Pre-Authorized
100% ESA inspection passing rate over the past 2 years