Some service upgrades happen mostly at the panel. This one started in the ground. A GTA home was getting a new 200 amp service fed underground, and we filmed it on a snowy day in March: the cable in the trench, the run along the foundation, the new meter base, and the utility reconnecting the power.
The job
This home was getting a new 200 amp underground service. That meant new service cable coming in underground, a new meter base on the house, and a reconnect by the utility once everything on our side was ready.
What we did, step by step
- The cable in the trench. The new service cable reaches the house through a trench. Red warning tape marked “electric line below” goes into the trench with it, so anyone digging there later knows there’s a live line underneath.
- Along the foundation. We ran the new service cable along the foundation, secured to the wall, up to the meter location.
- The new meter base. We installed a new meter base for the 200 amp service, with the conduit running down from it into the trench.
- Ready and waiting for hydro. At this point our installation was finished, but the meter base was still empty. That’s normal. The meter goes in when the utility reconnects the service, so the empty meter base in the video is finished work waiting for hydro.
- Utility reconnect. The utility crew came out and reconnected the service. With the meter in, the home was energized on its new 200 amp service.
- Finished. In the finished photo, the new meter is live and the trench is filled back in.
Why the order matters
A service upgrade isn’t only electrical work at the house. In Ontario it needs an ESA permit, and the local utility has to disconnect and reconnect the power. The utility reconnects once ESA has authorized the connection.
That’s why everything on our side has to be installed and ready before the utility crew arrives. When they get there, the job is waiting for them, not the other way around.
Underground services add steps of their own. The route has to be dug, the cable protected and marked, and some utilities review the design before they approve a bigger service.
When to think about a 200 amp service
If you’re planning a big new load, such as an EV charger, a heat pump, a hot tub or a basement unit, or your panel has no room left, a load calculation tells you whether your current service can carry it. Our post on 100 amp vs 200 amp panels explains how we make that call, and our panel and service upgrades page covers the work itself.
FAQ
Yes. This one was: new service cable underground and along the foundation, a new meter base, and a reconnect by the utility. Some utilities review the design first, so it starts with an assessment.
The installation was finished and waiting for the utility. The meter goes in when the utility reconnects the service, after ESA has authorized the connection.
The utility sets the schedule. Ideally it disconnects in the morning and reconnects in the afternoon, but plan for most of a day without power.